A flood overlay is a mapped planning control that says the land can flood, and it works by adding a layer of assessment on top of whatever the zone already allows. It rarely stops development outright. What it tends to do instead is set the level your floors have to sit at, limit how much you can fill, decide whether a ground floor or a basement is usable, and add a specialist report and sometimes a referral to the approval path. Each of those lands somewhere in the feasibility, and the one that hurts most is usually the one nobody priced.
The names change between jurisdictions. In New South Wales the control sits in the local environmental plan as a flood planning clause, and the land tends to appear as a flood control lot on a planning certificate. Victoria has three separate flood overlays. Queensland uses a flood hazard overlay in the local planning scheme. South Australia has a set of hazards overlays, Western Australia maps floodway and flood fringe areas, Tasmania runs a hazard code in the state planning provisions, and the Northern Territory applies a land subject to flooding overlay alongside one for storm surge. The mechanics rhyme even where the wording does not.
Two consultants hold most of the answers on a particular site. The flood engineer, sometimes engaged as a hydraulic or hydrology consultant, works out the flood level at your boundary, how deep and fast the water gets, whether the site sits in a flow path or a storage area, and whether a design can be lifted above it. The planner works out which overlay applies, what the local code or development control plan asks for beyond the overlay, and whether the application has to be referred to a floodplain or water authority that can refuse to consent. On sites in a mapped floodplain both answers bear directly on what the land is worth, which is why many developers get them before exchange rather than after.
Everything below was current in September 2026, and flood is a fast-moving area. Victoria is partway through a two-year mapping and controls rollout, South Australia has a state-wide flood hazard code amendment awaiting a decision, and Tasmania is rebuilding its flood mapping. Each figure and rule below links to the government page or the legislation it came from, and that link is where to confirm it on the day you need it.
What does a flood overlay actually control?
A flood overlay controls four things: the minimum level of floors, what can be built or filled in the parts of the floodplain that carry or store water, what has to be demonstrated in the application, and who gets to comment or consent.
The first is the one developers meet earliest, because it is arithmetic. A flood level is a height above the Australian Height Datum, the design has to sit above it by a set margin, and the difference between that height and your natural surface level is fill, a suspended floor, or a redesign.
The second is the one that quietly removes yield. Floodplains are not uniform. Part of a floodplain moves water, part of it stores water, and part of it is simply wet at the edges. The Queensland Reconstruction Authority describes flood storage areas as “the parts of the floodplain that are important for temporary storage of floodwaters during a flood passage”. Western Australia splits its mapping the same way, with the floodway defined by the Department of Water and Environmental Regulation as “the river channel and a portion of the floodplain where a significant flow or storage of water occurs”, where no new building development is permitted, and the flood fringe as “the area of the floodplain, outside of the floodway where development could be permitted” subject to flood hazard compatibility and building standards. Land in the first category tends to be unbuildable in practice, which is a yield question rather than a level question.
The third is documentation. On a flood affected site the application usually carries a flood study or flood impact assessment, and the test it has to satisfy is generally about effect on other people. Central Coast Council’s position on fill is blunt and typical: “Filling is not allowed in any areas considered to be a floodway, flow path or flood storage area.” If you raise your site out of the floodplain, the water goes somewhere else, and the assessment is where that shows up.
The fourth is the referral. In parts of Victoria the council cannot issue the permit without the floodplain authority’s consent, which puts a second decision maker in your programme.
What is a flood planning level, and how is it set?
A flood planning level is the height a design has to be built to, and it is made of two parts: a modelled flood level plus a safety margin called freeboard.
Northern Beaches Council states the New South Wales convention plainly, defining the flood planning level as “the 1% Annual Exceedance Probability (AEP) flood level (equivalent to the 1 in 100 year flood level) with a freeboard added”. Bayside Council puts the same definition alongside the margin it applies, describing the flood planning level as a height used to set floor levels for property development in flood prone areas, generally defined as the 1 per cent annual exceedance probability flood level plus an appropriate freeboard, and notes that “freeboard is usually 0.5m above a flood level” and may be higher for vulnerable uses such as hospitals or schools.
Queensland uses the same two-part structure with different labels. The Queensland Reconstruction Authority defines the defined flood event as “the flood event selected for the management of flood hazard to new development”, the defined flood level as “the level to which it is reasonably expected flood waters may rise”, freeboard as “the height above the defined flood level (DFL) as determined by the appropriate authority, typically used to compensate for effects such as wave action and localised hydraulic behaviour”, and the flood planning level as the adopted defined flood level combined “with a selected freeboard for floodplain management and development control purposes”. City of Gold Coast describes the margin it applies as “usually 30 to 50 centimetres”.
Three things follow for a feasibility.
The flood level is site specific and comes from a study, not from a map colour. The overlay tells you that you are affected. The level tells you by how much, and it can differ by hundreds of millimetres across a single site.
Freeboard is set by the authority, not by you, and it is not uniform across the country or across use types. Half a metre in one council and 300 millimetres in another is the difference between a slab on ground with imported fill and a suspended floor.
The design event is usually the 1% annual exceedance probability flood, described by the Department of Water and Environmental Regulation as a standard “generally adopted in Australia and overseas as the basis for floodplain management planning”. The annual exceedance probability is defined by the Queensland Reconstruction Authority as “the likelihood of the occurrence of a flood of a given or larger size occurring in any one year, usually expressed as a percentage”, so a 1% event is not a once in a century guarantee. Some controls also reach beyond it, up to the probable maximum flood, which the authority describes as a hypothetical estimate for a catchment whose magnitude is such that there is negligible chance of it being exceeded.
That last point matters more than it looks. A site can sit above the flood planning level and still be caught by controls, because the question the authority is asking is not only whether the building stays dry.
What do the flood overlays and codes look like in New South Wales?
In New South Wales the flood control generally sits in the council’s local environmental plan rather than in a separate overlay, and the land is identified through the planning certificate rather than on a public overlay map.
The New South Wales planning department’s flood prone land package, which commenced on 14 July 2021, put a flood planning clause into standard local environmental plans with the stated aim to “minimise the flood risk to life and property associated with the use of land within the flood planning area”. A second, optional clause dealing with special flood considerations was adopted by a minority of councils and reaches further, covering sensitive and hazardous development between the flood planning area and the probable maximum flood, and non-sensitive development where evacuation is the problem. The department also notes that flood maps were largely removed from local environmental plans and now sit with councils, in their own mapping or development control plans, which is why a site can be heavily flood constrained with nothing visible in the planning instrument itself.
The practical identifier is the planning certificate. Central Coast Council defines a flood control lot as “land parcel that is subject to flood related development controls, which is specified on a Section 10.7 Planning Certificate”. That makes the certificate the first document to read on any New South Wales site, and the section 10.7 certificate guide covers what else it discloses. Whether a complying development pathway survives on a flood control lot is a question for the certifier against the complying development codes rather than something the overlay answers, and it is worth asking early, because losing that pathway changes both the programme and the assessment risk.
Behind all of it sits the New South Wales Flood Risk Management Manual, which the Department of Climate Change, Energy, the Environment and Water records as having been “gazetted in June 2023” and as having “replaced the Floodplain development manual (2005)”. The manual was gazetted for the purposes of section 733 of the Local Government Act 1993 (NSW), the provision that gives councils protection where they act in good faith in accordance with the manual. Read from a developer’s side, that is a pointer to where risk sits: a council following the manual has a defence, and the person carrying the consequence of a flood affected design is generally the applicant.
What do Victoria’s three flood overlays do?
Victoria splits flood into three overlays, and which one applies changes both the severity of the constraint and who decides.
Melbourne Water describes them by the flooding they represent. The Floodway Overlay “applies to land that’s identified as carrying active flood flows associated with waterways and open drainage systems and high hazard areas”. The Land Subject to Inundation Overlay “typically applies to land affected by flooding associated with waterways and coastal areas”. The Special Building Overlay “identifies areas prone to stormwater, or overland flooding when the capacity of the drainage system is exceeded”, and it is the one that catches inner and middle suburban infill sites that are nowhere near a river.
The Victorian Planning Authority describes the purpose of the Land Subject to Inundation Overlay as being to “ensure development effectively responds to the flood hazard and will not cause any significant rise in flood level”, and the Floodway Overlay as applying to land at high risk of flooding with the aim to “ensure any development is compatible with the flood hazard, allowing the free passage of floodwater”. It also notes the referral mechanics: an application will be assessed by the relevant catchment management authority “through a formal referral” and proceeds only where “the flood hazard can be appropriately managed”.
In the Melbourne metropolitan area that authority is generally Melbourne Water, and its consent is a precondition, in its own words: “your council won’t issue you a planning permit unless your plans meet our criteria for flooding and we consent to your proposed work.” The five criteria it publishes are a useful checklist for any jurisdiction, because they are the questions a floodplain authority anywhere is asking. Works or structures must not affect floodwater flow capacity, must not reduce floodwater storage capacity, must “meet minimum floor level height (above flood level) relevant to development location (freeboard)”, must not occur where the depth and flow of floodwaters would create a hazard, and must not occur where the depth and flow of floodwater affecting access to the property is hazardous.
Two of those five are about other people’s water and one is about getting out, which is a reminder that a compliant floor level is necessary rather than sufficient.
Victoria is also mid-change. In October 2025 the department announced updated flood mapping for Greater Melbourne to be rolled out with Melbourne Water coordination and “progressively implemented into local planning schemes over the next two years”, together with risk-based controls sorting land into four tiers from very high risk, where development would be avoided, down to low risk, where “developments will only need to manage flood risk through the building system, avoiding the unnecessary delay of a planning application”. For a site you are looking at now, the live question is which map your application will be assessed against, and whether the study feeding it has already landed with the council.
How does Queensland map flood hazard?
Queensland puts flood hazard in the local planning scheme as an overlay with risk categories, and the state layer sits above it in the State Planning Policy.
Moreton Bay’s scheme is a fair example of the local structure. Its flood hazard overlay map “shows the location and extent of special features such as where land may be subject to hazards or other impacts”, it sorts land into high risk, medium risk and a balance flood planning area described as low to negligible risk, and the associated code “provides additional assessment benchmarks and development requirements over and above the ‘normal’ zoning or use requirements”. Risk categories are derived from depth and velocity of water as well as frequency of inundation, so two sites with the same flood level can land in different categories and attract different controls.
Brisbane runs the most developed property level information in the country. A FloodWise Property Report is based on “the latest adopted flood planning information in Council’s planning scheme, Brisbane City Plan 2014” and includes “estimated flood levels” and “habitable floor level requirements”. The council maps four flood sources, “river”, “creek”, “overland flow” and “storm tide”, and notes that flooding “can be a result of one or a combination of these 4 sources”. It distinguishes a residential flood level, which equates “to the 1% annual likelihood of flooding”, from a defined flood level “used for commercial and industrial developments”, and describes the Flood Overlay code as guiding “the future development of land at risk of flooding within Defined Flood Planning Areas (FPAs)”.
Two lessons transfer beyond Brisbane. The first is that a site can be clear of riverine flooding and still be caught by overland flow or storm tide, which are modelled separately. The second is that the applicable level can depend on what you are building, so a change of use or a mixed use scheme can change the level the design has to meet.
At state level, the Natural Hazards, Risk and Resilience state interest in the State Planning Policy is what pushes flood into local schemes. The department records the current policy as the 2017 version, with a draft revised State Planning Policy out for consultation at the time of writing, so the state framing may move while local overlays stay as mapped.
What applies in the other states and territories?
The constraint is the same everywhere. Where jurisdictions differ is in what the control is called, who holds the mapping, and how much of the assessment sits in planning rather than building.
South Australia
South Australia’s flood controls sit in the Planning and Design Code as a set of hazards overlays, split by how tolerable the risk is and by whether there is data at all. The state government describes three of them: a flooding hazards overlay applying “to areas that can be subject to an intolerable flood risk”, a general flooding hazards overlay applying “to areas with tolerable flood risk”, and an evidence required flooding hazards overlay applying “to areas where there is no suitable flood study data”.
That third overlay is the one to watch on a due diligence, because it shifts the burden. Where the state has no study, the applicant is the one who has to produce the evidence, and that is a cost and a programme item rather than a policy position.
A state-wide flood hazard code amendment initiated by the State Planning Commission on 12 December 2023 went to consultation during 2026, proposing “more consistent and updated mapping”, “improved planning rules” and “a faster process for future mapping updates”. The studies behind it modelled a one in 100 year flood to 2050 and classified hazard from H1 to H6 by depth and velocity. As at the date of writing the amendment is with the decision maker rather than in force, so PlanSA’s project page is where its status can be confirmed.
Western Australia
Western Australia’s floodplain mapping is maintained by the Department of Water and Environmental Regulation and splits the 1% annual exceedance probability floodplain into floodway and flood fringe. The distinction is the whole control. In a floodway, development that obstructs major flows is treated as unacceptable because it would increase flood levels upstream. In a flood fringe, development may be considered acceptable with building conditions that provide flood protection.
For a developer that produces a sharper site test than a single overlay boundary: the question is not whether the land floods but which of the two categories the developable footprint sits in, and whether the floodway crosses the part of the site you were counting on.
Tasmania
Tasmania runs flood through a hazard code in the state planning provisions rather than a council by council overlay, and the mapping is being rebuilt. The State Planning Office and State Emergency Service are jointly reviewing the mapping used in the flood-prone areas code, with the stated intention to “update statewide flood-prone area mapping and include a new Flood-Prone Areas Hazard Code, which integrates with the Coastal Inundation Hazard Code and the building system”. The first stage strategic flood maps “show the likely area of flooding, depth and speed of water, and danger to people and property”.
Two features are worth noting. Coastal inundation is handled as its own hazard code, so a coastal site can be caught by one, the other or both. And the review is not yet implemented in the planning scheme, which means the map the emergency service publishes and the map your application is assessed against may not be the same map.
Australian Capital Territory
The Australian Capital Territory publishes territory-wide flood modelling for the 1% annual exceedance probability event, described by the government as “a rare, but big, flooding event that has a 1% chance of happening in a year”, with mapping showing “how far the water might go”, “how deep the water might get” and “how fast the water might flow, which tells you how risky it could be”. The government is candid about the limits, noting the maps “don’t know how blocked drains or broken water systems will change the water flow”. On a Canberra site the modelling is the starting point and the site specific work still sits with a flood engineer.
Northern Territory
The Northern Territory applies two overlays: a land subject to flooding overlay for riverine flooding and a land subject to storm surge overlay for coastal inundation. The government describes both as applying “additional requirements to developments” in the mapped areas to minimise “risk to people, damage to property, cost to the general community”, with storm surge split into primary and secondary areas. It also points developers to a building certifier for how the requirements are met in practice, which reflects how much of the Northern Territory response sits on the building side.
How do you find out whether a site is flood affected before you exchange?
The reliable sequence is a public map for triage, a council or authority certificate for the adopted levels, and a surveyor and flood engineer for the numbers you will actually design to.
Public mapping is free and fast, and it differs by state. VicPlan is described by the Victorian department as “a state wide map viewer for location based planning scheme information” that lets you “find a property or parcel, generate a planning property report, and view zones and overlays anywhere in Victoria”, and the planning property report is the document to pull first on any Victorian site. FloodCheck Queensland is “a web map application that provides information on flood plains, modelled and historic flood maps, imagery and reports”, though it carries an important warning: it shows where flood studies exist rather than the actual risk at a property, and property level risk comes from the council. The Australian Capital Territory publishes its modelling through its own mapping platform.
Adopted levels come from the authority. Brisbane’s FloodWise Property Report gives estimated flood levels and habitable floor level requirements for an address. Melbourne Water issues a property flood level certificate on application for a published fee. Councils in New South Wales generally issue flood information on request, with Central Coast Council publishing a standard flood information certificate “delivered within 15 business days” and an urgent one “delivered within 3 business days” at the time of writing. Those turnarounds sit awkwardly against a short due diligence period, since 15 business days inside a 30 day window leaves very little room for the flood study that follows, and a compressed timetable is where flood risk most often gets accepted by accident. The contract side of that, how long the due diligence period runs and what it allows if the authority’s information arrives late, is a legal question rather than a planning one.
The numbers you design to need two more inputs. A feature and level survey sets your natural surface levels to the Australian Height Datum so the flood level and the site can be compared at all, and that is the land surveyor’s work. A flood study or flood impact assessment by a flood engineer then converts the level into a design response, and on a constrained site it also tells you whether the response is viable before you have paid for an architect to draw it.
What does a flood overlay do to yield and to what you can build?
The yield effect runs through three mechanisms, and only the first is obvious.
Lifting the building is the obvious one. If the flood planning level sits a metre above natural surface, the ground floor goes up, and whatever height the scheme was using at the top now competes with a height limit that has not moved. On a site with a tight building envelope, a metre of fill can cost a storey, and that is a yield loss rather than a cost increase.
Losing part of the developable area is the quieter one. Where a floodway, a flow path or a flood storage area crosses the site, the usable footprint shrinks, and the affected land often cannot be filled or compensated for. A site that measured well on a title plan can measure badly once the flow path is drawn on it, which is a reason the flood engineer’s advice tends to reshape the yield assumption that a highest and best use analysis started from.
Losing the use of the lowest level is the one that hits revenue hardest. Basement and undercroft parking, storage, plant rooms and ground floor commercial tenancies all sit at the levels a flood control is most likely to restrict, and the responses each carry a cost: raising the ramp crest, flood gates or barriers, relocating plant and switchboards above the flood planning level, or giving up the level entirely. Where a ground floor tenancy becomes unlettable at the required level, the loss shows up in gross realisation rather than in the build cost.
Access and evacuation sit alongside all three. Melbourne Water’s criteria include not developing where the depth and flow of floodwater affecting access is hazardous, and the New South Wales special flood considerations clause reaches non-sensitive development where evacuation risk is the issue. A site can therefore be capable of a dry building and still fail on the road out, and that is a constraint no amount of fill fixes.
What does the National Construction Code require in a flood hazard area?
On the building side, construction in a designated flood hazard area is generally handled by reference to a dedicated standard rather than by provisions written out in the code itself.
The Australian Building Codes Board publishes the Standard for Construction of Buildings in Flood Hazard Areas, and the National Construction Code links compliance to it. In the 2022 Volume Two provisions as adopted, the performance requirement for Class 1 buildings in a flood hazard area “is satisfied if the building is constructed in accordance with the ABCB Standard for Construction of Buildings in Flood Hazard Areas”, with flood hazard area, freeboard and defined flood level appearing as defined terms that states and territories vary.
Three points matter for a developer. The building side only engages where an authority has designated a flood hazard area, so the planning mapping and the building trigger are linked but not identical. Because the key terms are subject to state variation, the same design can meet the requirement in one jurisdiction and not in another. And a newer edition of the National Construction Code is being adopted on a staged basis by the states, so the edition applying to a building approval depends on when that approval is lodged in that jurisdiction, which is worth confirming with the certifier on a project whose approval straddles an adoption date.
What does a flood overlay do to construction cost and programme?
The cost effect is rarely a single big number. It tends to be several medium ones, spread across earthworks, structure, services and consultants, which is why it is often missed in an early feasibility built from a cost rate per square metre.
The earthworks line moves first, through imported fill, its compaction and testing, retaining where fill meets a boundary, and the drainage that the raised surface now needs. Where fill is not permitted, the cost moves into structure instead, as a suspended slab, deeper footings, or a raised podium, which is generally the more expensive of the two answers. Services follow, since switchboards, pumps, lifts, fire services and plant that sit below the flood planning level either move or get protected. Landscape and access then absorb the level change, through regraded driveways, ramps and accessible paths that have to reconcile a raised floor with an unchanged street level. Because these are level driven rather than area driven, they scale with the height you have to gain rather than with the size of the building, so a cost rate per square metre carried over from an unconstrained project understates them.
Consultant cost is the smaller line that changes the decision more often, because it arrives before commitment. A flood study, a flood impact assessment, hydraulic modelling of the effect on neighbouring land, and a civil engineer’s response to it are all pre-approval spend on a site you may not proceed with.
Programme is where flood constraints do their real damage. The sequence usually runs: level survey, flood information from the authority, flood study, design response, then lodgement, with a referral to a floodplain authority sitting inside the assessment. Where the authority does not consent, the loop repeats with a redesign. Every week of that sits in land holding costs and in the interest bill, and on a site bought unconditionally it sits there whether or not the scheme survives the process. Where the mapping itself is being updated, as in Victoria and potentially in South Australia and Tasmania, there is a second programme risk: an application lodged against one map and assessed against another.
The general point for a feasibility is that flood risk on a constrained site is not well handled by a single allowance. It is a set of identifiable items with a separate, and much larger, tail risk that the design response is refused, which is a different thing from the construction contingency that covers cost variance on a scheme already approved.
What does a flood overlay do to land value?
Flood constraints show up in the land price, because the residual is what absorbs them. The arithmetic is worth doing explicitly, since the size of the shift tends to surprise people who have treated flood as a construction cost item.
Take an illustrative townhouse site, with round figures chosen to make the arithmetic followable rather than to represent any market. The unconstrained scheme is 18 townhouses at an average $1,000,000, so gross realisation is $18,000,000. Construction runs at $550,000 each, or $9,900,000, and consultants, contributions, marketing, selling and finance come to $1,800,000, so total development cost excluding land is $11,700,000. At a target 20% margin on cost, total cost including land is $18,000,000 divided by 1.2, or $15,000,000, which leaves $3,300,000 for the land.
Now apply a flood constraint, changing three inputs. A mapped flow path across the rear of the site removes two townhouses, so 16 remain and gross realisation falls to $16,000,000. Flood related works add $30,000 per dwelling, or $480,000, on top of $8,800,000 of base construction, giving $9,280,000. Soft costs fall slightly with the smaller scheme to $1,700,000 but carry an extra $150,000 for the flood study, hydraulic engineering and the longer assessment, giving $1,850,000. Total development cost excluding land is therefore $11,130,000. Holding the same 20% margin on cost, total cost including land is $16,000,000 divided by 1.2, or $13,333,000, which leaves about $2,203,000 for the land.
The land value has moved from $3,300,000 to roughly $2,203,000, a reduction of about $1,097,000, or a third. The whole of the reduction comes from the revenue side. Losing two dwellings takes $1,667,000 off what the land can bear at a 20% margin, and the cost changes push the other way by $570,000, because two fewer townhouses cost less to build even with the flood works added. A developer who prices the fill and the suspended slab but keeps the original yield has not priced the constraint at all.
A second implication follows for anyone bidding against a competitor on the same site. Where the flood mapping is public but the site specific level is not, the bidder who has the flood engineer’s advice is working from a different land value than the one who has read the overlay alone, and the gap between those two numbers is roughly what an unpriced flow path is worth.
Why are flood levels being redrawn, and what does that mean for a site you buy now?
Flood mapping across Australia is being updated, and the direction of travel is toward more land mapped, more detail in the mapping, and levels that account for a future climate rather than a historical record.
Design flood estimation in Australia rests on Australian Rainfall and Runoff, described by Geoscience Australia as providing “the best available information on Australian design flood estimation techniques” and published by the Commonwealth. The current edition is the fourth, published in 2019, with the first having appeared in 1958. Because flood studies are built on that guidance and on the catchment data available when they were run, a study prepared a decade ago and a study prepared this year can produce different levels on the same land without anyone changing the law.
Three live programmes show the pattern. Victoria’s October 2025 announcement pairs updated Melbourne Water mapping with risk-based planning and building controls, to be implemented in local planning schemes over about two years. South Australia’s state-wide flood hazard code amendment proposes updated mapping and policy, with its consultation closed and a decision pending. Tasmania’s strategic flood mapping work is intended to produce a new flood-prone areas hazard code integrated with the coastal inundation code and the building system. New South Wales gazetted its Flood Risk Management Manual in June 2023, replacing a manual that had stood since 2005.
For a site under consideration now, that raises a question the overlay cannot answer: which map will this application be assessed against, and is a study in progress that would change the level. A council or authority can usually say whether a new flood study is underway in the catchment. Where one is, the timing risk runs both ways, since a level can fall as well as rise, and a design tuned to the current level can become non-compliant before lodgement.
How does New Zealand treat flood-prone land?
New Zealand handles flood through a combination of district plan hazard provisions, a subdivision consent power and building consent provisions that can put a notice on the title.
On the planning side, natural hazards including inundation are a matter a council weighs under the Resource Management Act 1991, and section 106 allows a consent authority to refuse a subdivision consent, or grant it subject to conditions, where there is a significant risk from natural hazards. That is a stronger tool than it first appears, because it applies to the creation of the lots themselves rather than only to what is built on them. The resource consent process is where that assessment is made, and the wider reform of New Zealand’s resource management system means the provisions and the plans they sit under are both in transition.
On the building side, sections 71 to 74 of the Building Act 2004 deal with building on land subject to a natural hazard. The Ministry of Business, Innovation and Employment summarises the requirement as being to “consider the effect of the building work on the natural hazard, and also consider how you could protect the land, building and other property when undertaking building work on land subject to a natural hazard”, and notes that where work does proceed “there is a requirement for a notice to be placed on the record of title for the property so that future owners are aware that the land is subject to a natural hazard”.
That notice is the part with a commercial tail. A notice on the record of title travels with the land, is visible to every future purchaser and their advisers, and is a disclosure question on resale rather than a construction question during the build.
What are the traps developers actually hit?
The trap is rarely the flood level itself. It is the gap between when the constraint becomes knowable and when the deal becomes unconditional.
Treating the overlay boundary as the constraint. The overlay says you are affected. The flood study says by how much, where the flow path runs, and whether the footprint you priced survives. Those are different documents with different answers, and only one of them is free.
Pricing the level and ignoring the yield. Fill and suspended slabs are visible and estimable. Two lost dwellings, an unlettable ground floor tenancy or a deleted basement level are neither, and they are usually larger.
Assuming fill solves it. Where the land is a floodway, a flow path or a flood storage area, filling tends to be prohibited outright rather than conditioned, because the water has to go somewhere and the assessment is about the effect on everyone else.
Forgetting the road out. Access and evacuation are assessed separately from floor levels, and a dry building on an inaccessible site can still fail.
Missing the referral. Where a floodplain or water authority has to consent, there is a second decision maker with its own timeframe and its own criteria, and the council cannot override it.
Working from a superseded map. Where a new flood study or a code amendment is in train, the level current at lodgement may not be the level current at determination.
Relying on the wrong flood source. River, creek, overland flow and storm tide are modelled separately, and an inner suburban infill site well away from a waterway is most often caught by the overland flow or stormwater layer.
Buying unconditionally inside a short due diligence period. Authority turnarounds for flood information run to weeks rather than days, and a flood study takes longer again, so the timetable itself can be the reason a constraint gets accepted unpriced.
What to ask your flood engineer, your planner and your lawyer
The questions below are the ones that decide a flood affected site on its own facts, and they are the ones this guide deliberately does not answer.
For the flood engineer or hydraulic consultant
- What is the modelled flood level at each part of this site for the design event the authority adopts, and how much does it vary across the site?
- Does any part of the site sit in a floodway, a flow path or a flood storage area, and how much of the developable footprint does that remove?
- Which flood sources have been modelled for this land, and is there an overland flow or stormwater layer as well as a riverine one?
- What freeboard will this authority apply to this use, and does it change if the use or the building class changes?
- What is the fall from the flood planning level to natural surface across the footprint, and what does that mean in cubic metres of fill or square metres of suspended floor?
- Is fill permitted here at all, and if it is, what compensatory works or hydraulic modelling of the effect on neighbouring land will the authority expect?
- Is access to the site trafficable in the design event, and would evacuation be assessed as safe?
- Is a new flood study underway in this catchment, and if so, what is the risk the adopted level changes before determination?
For the town planner
- Which overlay, clause or code applies to this land, and what does the local development control plan or code require beyond the overlay itself?
- Is a referral to a floodplain, catchment or water authority triggered, and is its consent a precondition to the permit?
- Does the flood control remove any faster assessment pathway that the site would otherwise have had?
- Do controls extend above the flood planning level, up to the probable maximum flood, for the use proposed?
- What has this authority actually approved on comparable flood affected land recently, and on what design response?
- How does the flood response interact with the height control, and does lifting the floor cost a storey?
- If mapping or controls in this jurisdiction are being updated, what is the timing, and which version is likely to apply to this application?
For the lawyer
- What does the planning certificate or its equivalent disclose about flood related development controls on this land, and what does it not disclose?
- Is the due diligence period long enough to obtain the authority’s flood information and a flood study, and what does the contract allow if it is not?
- What did the vendor disclose about flooding, and what recourse exists if the flood constraint proves worse than disclosed?
- Are there existing notices, agreements, easements or drainage reserves on title connected to flooding or overland flow?
- On a New Zealand site, does a notice under the Building Act 2004 sit on the record of title, or is one likely to be required?
Where to check the figures
- NSW flood prone land package, Department of Planning, Housing and Infrastructure
- NSW Flood Risk Management Manual, Department of Climate Change, Energy, the Environment and Water
- Flood planning level and freeboard, Bayside Council and Northern Beaches Council
- Flood control lots and flood certificates, Central Coast Council
- Victoria’s flood planning controls explained, Melbourne Water and its consent criteria
- Land Subject to Inundation and Floodway overlays, Victorian Planning Authority
- Updated Victorian flood mapping and controls and VicPlan
- Flood terms and definitions, Queensland Reconstruction Authority
- FloodWise Property Reports, Brisbane City Council, Planning for flood, City of Gold Coast, flood hazard overlay, City of Moreton Bay and FloodCheck Queensland
- Queensland State Planning Policy
- South Australia’s state-wide flood hazard code amendment and PlanSA hazard mapping project
- Floodway and flood fringe mapping, Department of Water and Environmental Regulation
- Flood-prone areas code review, Planning in Tasmania
- Flood maps, ACT Government
- Planning and building rules for land affected by natural hazards, Northern Territory Government
- Standard for Construction of Buildings in Flood Hazard Areas, Australian Building Codes Board and the National Construction Code Volume Two structure provisions
- Australian Rainfall and Runoff and Geoscience Australia’s overview
- Natural hazard sections of the Building Act 2004, Ministry of Business, Innovation and Employment and section 106 of the Resource Management Act 1991, Quality Planning